|
On
the Rebound
As we all realize, the tragic events of September
11, 2001 have changed our lives forever. Likewise, the many industries
which support and service our national aviation system have been affected
in far reaching ways.
Commercial and general aviation have seen budgets slashed and reappropriated
like never before. Aviation spending in the aftermath of 9/11 is appropriately
dominated by increased security measures while expansion projects have
been cancelled or put on hold until budget concerns are alleviated.
Indeed, these are very tryin gtimes for the aviation community.
Yet, our aviation system will rebound and become stronger as a result
of these events and general aviation, as always, will be major player.
In fact, GA may play a larger role as many travelers experience the
efficiency and safety of private aircraft for the first time.
In this issue of "T-Hangar Times" , we focus on an impressive
example of general aviation growth at Frederick Municpal Airport (FDK)
in Maryland. Thanks to the collective efforts of dedicated airport officials
and local private sector interests, the airport recently completed its
first T-Hangar development in over 50 years. We are proud to have been
a part of this 80 unit project, which is overlooked by AOPA's National
headquarters.
Frederick Municipal Airport
In December of 1999, the T-Hangar Task Force at the
Frederick Municap Airport invited Fulfab to a meeting to discuss plans
for their T-Hangar project. The comments and suggestions made at that
meeting were incorporated into plans and specifications published in
October of 2000.
On December 5, 2000, the city of Frederick received
bids for eighty units of bifold door T-Hangars along with drainage and
site improvements. The successful bidder was C.William Hetzer, Inc.
A general contractor from Hagerstown, Maryland.During the next three
months, the general contractor carefully evaluated T-Hangar proposals
from three manufacturers. Fulfab's was the on ly proposal to feature
a fully-integrated building and bifold door system with steel erection
performed by the hangar manufacturer. In mid-March of 2001, Fulfab was
awarded a contract to furnish and erect seven T-Hangar buildings housing
a total of eighty aircraft. Within two weeks after award of contract,
drawings were prepared, sealed and submitted to the City of Frederick
for plan review and permit purposes. Six of the seven buildings were
twelve unit Model LK42 Hangars with 42' x 12' bifold doors. The seventh
building was an eight unit Model LK48 Hangar with 48' x 14' bifold doors.
Since each building comprised an area greater than
12,000 square feet, a fire separation wall was required in the middle
of each building. Other features common to each building were full-height
interior partition wallsl, a door and window in each corner space, and
two inch thick fiberglass roof insulation. The southernmost building
was also equipped with restroom facilities.
The general contractor began the extensive drainage
and site work on April 2, 2001. The allotted time for completion was
250 calendar days with a $1,000 per day penalty for late completion.
Fulfab was contractually obligated to complete the steel erection within
fifteen consecutive weeks. Working from North to South, the general
contractor provided the first two building sites to us in the first
half of August.
Steel erection work began on August 21, with one crew on site. Two weeks
later the first building was nearly complete and ready for the electrical
and firewall contractors to begin. At that time the next two buildings
were delivered and two Fulfab crews began working simultaneously. Two
of our erection crews were on site for approximately half the duration
of the job.Thirteen weeks after starting, the seventh building was completed
on November 19, and turned over to the other subcontractors. Two years
of planning and work came to fruition on December 13, 2001, when a T-Hangar
dedication and ribbon cutting ceremony was held. Phil Boyer, President
of the Aircraft Owners and Pilots Association, along with Bruce Mundle,
Director of the Maryland Office of Regional Aviation Assistance were
among those who helped dedicate the hangar complex.
The
following is an excerpt from a letter to Fulfab from the Project Manager
for the Frederick Municipal Airport job.
"As our project comes to a close, I
want to take this opportunity to thank Fulfab and you personally for
your efforts in constructing the "T"-hangar buildings at the
Frederick Municipal Airport. Fulfab exceeded my expectations beginning
with the cooperation received in the bid process and continuing through
the completion of final punch list items. In particular I attribute
your professionalism and attention to detail during the submittal phase
for helping us overcome what might have been a regulatory nightmare.
I'm not quite sure how the problem would have been resolved without
your expertise.
Also, please extend my sincere gratitude to everyone
in your construction crew. I received excellent field reports on their
willingness to work with other building trades and for their expert
workmanship. As a result, the hangars were finished on-time and on-budget
which is the basic goal all project managers strive to achieve."
Maintenance Guide & Checklist

We recommend that you inspect and lubricate your Fulfab
T-Hangars and bifold doors at regular six month intervals. Reproduced
above is our maintenance checklist with procedures that should be performed
on each bifold door hangar unit.
Each procedure is referenced on the checklist with a drawing
number which will help you to locate the parts requiring your attention.
We can provide copies of these drawings to you free of charge.
Any worn or damaged parts should be reported and replacement
parts secured before the doors are used further. Fulfab maintains a
complete stock of replacement parts. |